Remove the three screws (Item 1) [Figure 20-40-93] from the spool centering block.
Installation: Tighten the bolt to 90 – 100 in.-lb. (10 – 11,3 Nโขm) torque.
Remove the spool centering block (Item 2) [Figure 20-40-93] from the control valve.
Remove the spring (Item 1) and center spring retainer (Item 2) [Figure 20-40-94] from the auxiliary spool.
Note: If the centering spring retainer (Item 2) [Figure 20-40-94] must be replaced, replace the retainer on the opposite end also.
Remove the spacer (Item 1) and O-ring (Item 2) [Figure 20-40-95] from the auxiliary spool.
Remove the spring (Item 1) and center spring retainer (Item 2) [Figure 20-40-96] from the auxiliary spool.
NOTE: If the centering spring retainer (Item 2) [Figure 20-40-96] must be replaced, replace the retainer on the opposite end also.
Remove the spacer (Item 1) and O-ring (Item 2) [Figure 20-40-97] from the auxiliary spool.
Remove the spool (Item 1) [Figure 20-40-98].